  • Address: 
  • Project Type: Addition, 8 Classrooms
  • Approval: Ministry of Education and Child Care approval August 12, 2021
  • Current Phase: Construction 82%
  • Construction Contract: Pro-Can Construction Group Corp.
  • Target Occupancy: May 2025

  • Address: 
  • Project Type: Addition, 10 Classrooms
  • Approval: Ministry of Education and Child Care approval August 12, 2021
  • Current Phase: Construction 80%
  • Construction Contract: Halse-Martin Construction Co. Ltd.
  • Target Occupancy: May 2025

Snokomish Elementary New School (Site 115)

  • Address: 
  • Project Type: New School, 27 Classrooms
  • Approval: Ministry of Education and Child Care approval March 30, 2021
  • Current Phase: Construction 47%
  • Construction Contract: D.G.S. Construction Company Ltd.
  • Target Occupancy: March 2026

Woodland Park Elementary Prefab Addition (Site 145)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 16 Classrooms 
  • Approval: Ministry of Education and Child Care approval September 27, 2023
  • Current Phase: Construction 50%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: Fall 2024

Walnut Road Elementary Prefab Addition (Site 152)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 12 Classrooms + 4 (16 total)
  • Approval: Ministry of Education and Child Care approval September 27, 2023
  • Current Phase: Construction 85%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: Fall 2024 (12-Classrooms); Fall 2025 (additional 4-Classrooms)

Lena Shaw Elementary Prefab Addition (Site 055)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 8 Classrooms
  • Approval: Ministry of Education and Child Care approval September 27, 2023
  • Current Phase: Construction 65%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: Fall 2024

  • Address: 
  • Project Type: Addition, 20 Classrooms
  • Approval: Ministry of Education and Child Care approval January 10, 2023
  • Current Phase: Design
  • Tender: Spring 2025
  • Target Occupancy: Fall 2027

  • Address: 
  • Project Type: Addition, 18 Classrooms
  • Approval: Ministry of Education and Child Care approval May 26, 2023
  • Current Phase: Design
  • Construction Management Services: Unitech Construction Management
  • Tender: Fall 2025
  • Target Occupancy: Spring 2028

  • Address: 
  • Project Type: Addition, 23 Classrooms
  • Approval: Ministry of Education and Child Care approval May 9, 2023
  • Current Phase: Design
  • Tender: Fall 2025
  • Target Occupancy: Spring 2028

Fleetwood Park Secondary Addition (Site 167)

  • Address: 
  • Project Type: Addition, 20 Classrooms
  • Approval: Ministry of Education and Child Care approval June 27, 2024
  • Current Phase: Design
  • Tender: Fall 2026
  • Target Occupancy: January 2029

Forsyth Road Elementary Addition (Site 183) 

  • Address: 
  • Project Type: Addition, 8 Classrooms
  • Approval: Ministry of Education and Child Care approval June 10, 2024
  • Current Phase: Design
  • Tender: Spring 2026
  • Target Occupancy: Fall 2028

Old Yale Road Elementary Prefab Addition (Site 064)

  • Address: 
  • Project Type: Pre-fabricated Modular Addition, 10 Classrooms + 7 More (17 total)
  • Approval: Ministry of Education and Child Care approval May 16, 2024 for 10 classrooms; July 5, 2024 for additional 7 classrooms
  • Current Phase: Design
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Tender: TBD
  • Target Occupancy: TBD

Martha Currie Elementary Prefab Addition (Site 061)

  • Address: 
  • Project: Pre-fabricated Modular Addition, 6 Classrooms
  • Approval: Ministry of Education and Child Care approval May 16, 2024
  • Current Phase: Design
  • Construction Management Services: Unitech Construction Management
  • Tender: TBD
  • Target Occupancy: TBD

Latimer Road Elementary Prefab Addition (Site 035)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 6 Classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Design
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Tender: TBD
  • Target Occupancy: TBD

William Watson Elementary Prefab Addition (Site 057)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 12 Classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Design
  • Tender: TBD
  • Target Occupancy: TBD

George Greenaway Elementary Prefab Addition (Site 090)

  • Address: 
  • Project Type: Addition, 20 Classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Design
  • Construction Management Services: Unitech Construction Management
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval

Clayton Heights Secondary Addition (Site 175)

  • Address: 
  • Project Type: Addition, 20 Classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Planning
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval

Darts Hill Area New Elementary School (Site 214)

  • Address: 17320 and 17390 20 Avenue area
  • Project Type: New School, 37 Classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Planning
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval

Grandview Heights Secondary Addition (Site 177)

  • Address: 
  • Project Type: Addition, 20 Classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Planning
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval